Work package 1

Management and Coordination

Lead beneficiary : SWRI

      Start Month    1              End Month    36

Participant numberShort name of participantPerson months per participant
1SWRI17
2CERTH0.5
3MGRE1
4THL1.5
5CUT0.5
6POLIBA1
7FST1
8MEU1

Objectives
To coordinate and manage MEDSAL project during its lifetime, monitoring efficiently project deliverables within the budgetary and time limits agreed and compliance with the PRIMA rules and Consortium Agreement.

Description of work
This WP constitutes the backbone of the Project, as it will pursue during its lifetime to run smothly, timely and succesfully all scientific, financial, and organizational aspects of the Project. Being an horizontal WP, interacts with all other WPs to ensure contigency according to the defined Project Management Plan and the steering decisions of its envisaged management bodies.

Deliverables

WPsTasks LeadersPPs InvolvedDuration
T1.1Start-up activities SWRIAllM1-M3
T1.2Web-based monitoring and management tool SWRISWRIM1-M4
T1.3Financial and Administrative Management of the ProjectSWRISWRIΜ1-Μ36
T1.4Monitoring and coordination of technical activities SWRISWRIΜ1-Μ36